Malaysia Plans Data Centre Disclosure Law as Power Use Comes Under Scrutiny
马来西亚拟立法要求数据中心披露用电:117个获批项目最大需求约23.5 GW
Malaysia's investment, trade and industry minister Johari Abdul Ghani said on November 12 that data centre disclosure requirements will be put into law, covering electricity use, imported GPUs and operating companies. Of 117 approved projects, 55 are operating and 19 under construction, with combined maximum power demand of about 23,500 MW. Official figures showed data centres had contracted 2,346 MW but were drawing only 1,374 MW as of August — a 972 MW gap — while data centres accounted for RM95.8 billion, or 43.9%, of approved investment in the first half of 2026.
Editor's note Malaysia's approved data centres claim about 23.5 GW of maximum demand, yet contracted load is 2,346 MW and actual draw only 1,374 MW. That booked-but-unused capacity is exactly the gap the planned disclosure law targets, with 55 of 117 projects now operating.