Taiwan's Economy Ministry Warns Forced Early Coal Retirements Covering 9.72 GW Could Push Reserve Margins Negative
台湾经济部:强制燃煤机组提前除役涉9.72 GW,2028、2029年备用容量率恐暴跌为负值
Taiwan's Energy Administration said on November 12 that a proposed air-pollution law amendment forcing early coal retirements would take 9.72 GW offline — Taichung's eight units at 4.4 GW, Heping at 1.32 GW, Linkou at 2.4 GW and Dalin at 1.6 GW — pushing reserve margins negative in 2028 and 2029 and affecting about 58 billion kWh a year, more than households' 51 billion kWh use in 2025. The economy minister said 25 large gas units adding 26 GW are due over ten years but take six to seven years to build.