CEC Reports 12.6 GW/39.36 GWh of New Electrochemical Energy Storage in Q3 2026

中电联统计:2026年三季度新投运电化学储能87座、12.6 GW/39.36 GWh

StorageSource:TaiyangNews(引中国电力企业联合会) · Source date · Added

Enterprises within the China Electricity Council's statistical scope commissioned 87 new electrochemical energy storage stations in the third quarter of 2026, adding 12.6 GW/39.36 GWh, TaiyangNews reported on November 13. Additions rose 172% year on year and 3% quarter on quarter, with Inner Mongolia, Xinjiang, Hebei, Shanxi and Shandong the top five regions. By the end of the quarter, the CEC's statistics covered 2,363 operating electrochemical storage stations totalling 143.53 GW/375.80 GWh.

Editor's note The quarter added 12.6 GW/39.36 GWh — an average duration of about 3.1 hours on the new build, in line with the roughly 3-hour fleet direction in the new implementation plan. The CEC total is an electrochemical-only statistical scope, however, and is not the same measure as the NEA's all-route new-type storage figure.
Read the original(TaiyangNews(引中国电力企业联合会))↗

More in this section · Storage

Daily digest

Daily digest 2026-11-14