Zhuanghe Pumped Storage Plant Advances: RMB 6.798 Billion, 1 GW, Five of Seven Underground Powerhouse Layers Excavated
庄河抽水蓄能电站建设提速:投资67.98亿元、100万千瓦,地下厂房七层已完成五层开挖,累计投资18.3亿元
Construction of the State Grid Xinyuan Zhuanghe pumped storage plant in Zhuanghe, Liaoning — a project listed in the national 14th Five-Year Plan — is pressing ahead in the mountains of Guiyunhua and Buyunshan townships, China Daily's Liaoning channel reported on November 16, citing Dalian News Media Group. The project, under construction since late 2022, carries a planned total investment of RMB 6.798 billion and an installed capacity of 1 GW, with four reversible pump-turbine generator-motor units of 250 MW each. Its main structures comprise an upper reservoir, a lower reservoir, water conveyance systems, an underground powerhouse system and a 500 kV ground switch station. Five of the seven layers of the underground powerhouse have completed excavation and support, with the sixth under way, and cumulative investment has reached RMB 1.83 billion. Once built, the plant will mainly undertake peak regulation, frequency regulation, phase modulation, energy storage and system reserve for the Northeast grid, with expected annual generation of 1.2 billion kWh and annual tax revenue of RMB 100 million.
Read the original(中国日报网(大连新闻传媒集团))↗